Cherry Park Elementary School Bond Updates

Project Scope Summary

Current Construction Timeline

ArchitectBBL Architect
Contractor (CMGC)Emerick Construction
Project Budgeton budget
Project Scheduleon Schedule
PermitApproved
ConstructionSummer 2024
Move Back InFall 2024
  • Current Project Status –
    • Design/Bid Phase complete.
    • Permits are approved and issued.
    • Repair/Renovation scopes are ongoing; currently, there are no concerns with finishing scopes of work over the summer schedule.
    • No District Staff onsite for duration of summer construction schedule.
ArchitectBBL Architect
Contractor (CMGC)Emerick Construction
Project Budgeton budget
Project Scheduleon Schedule
PermitNovember 2023 – April 2024
ConstructionSummer 2024
Owner Move Back InFall 2024
  • Current Project Status –
    • Design/Bid Phase complete.
    • Permits are approved and issued.
    • Bids were received January 11, 2024. Bids were under the target budget and the contract was awarded to Emerick Construction.
    • Pre-Construction meetings are ongoing to assure project success.
    • Ongoing communications with site staff on expectations for summers scopes of work continues.

All Educational Facility Sites: Intercom & Clocks

ArchitectLandis Consulting
Contractor (CMGC)GB Manchester. The Electrical Contractor
Project Budgeton budget
Project Scheduleon Schedule
DesignJanuary 2024 – March 2026
BiddingApril 2024
ConstructionSummer 2024 – Summer 2026 (Multiple Summers)

Repairs/Renovations

  • Construction scheduled to commence June 2024 and be substantially completed in August 2024
  • Target Completion date: August 2024
DesignComplete
BiddingComplete
PermitSubmitted and under review with City of Portland
General ContractorEmerick Construction
Pre-ConstructionOngoing with general contractor
Bi-weekly meetingsOngoing with staff to coordinate, communicate, and prepare for summer construction

All Educational Facility Sites: Intercom & Clocks

  • Construction is scheduled to commence in June 2024 and be substantially completed in July 2026. This scope will be at all educational facilities and will be completed over the next three summers. 
  • Target Completion date: Fall of 2024
  • Finalizing standards with DDSD stakeholders and the design teams.
DesignOngoing
BiddingOngoing