David Douglas High School Bond Updates

Project Scope Summary

Priority 1 ProjectAmountStart & End Date
Future Careers Building46,300,0002023 – Fall 2025
DDHS RenovationsAmountStart & End Date
Replace lighting for football and baseball fields3,600,000Feb. 2025 – Dec. 2026
DDHS North RenovationsAmountStart & End Date
Replace existing generator and add additional emergency11,300,0002023 – Dec. 2024
Replace Sprayed on ceiling finishes in north building
Replace north building drive system on bleachers
Partial replacement of roofing on north building
Replace some of domestic water supply in north building
Replace a portion of sewer at north building
Remodel entry for a secure vestibule
DDHS South RenovationsAmountStart & End Date
Replace fire alarm system in south building13,150,000Jan. 2024 – Dec. 2025
Remodel main entry area in south building
Replace part of roof on south building and part of PAC
Replace some of domestic water supply line in south building
Replace damaged roof structure
DDHS PAC RenovationsAmountStart & End Date
Upgrade some theatre lighting at PAC1,390,000Feb. 2025–Dec. 2026
Upgrade some theater systems at PAC
Aquatic Center RenovationsAmountStart & End Date
Replace 5 Tier Bleachers150,000Feb. 2025–Dec. 2026
Add nonslip texture to pool deck
Upgrade Intercom Systems & Some Clock Systems (All Educational Facility Sites)8,005,000July 2023–December 2026

Current Construction Timeline

DDHS CTE

ArchitectBRIC Architects
Contractor (CMGC)Pence Contractors
Project Budgeton budget
Project ScheduleBehind Target Schedule due to permitting issues
DesignMay 2023 – March 2024
PermitNovember 2023 – June 2024
BiddingDecember 2023 – March 2024
ConstructionApril 2024 – August 2025
Move InFall / Winter 2025
  • Current Project Status:
    • Land Use Permit started with City of Portland on Summer 2023.
    • Building Permit was submitted to City of Portland on 1/19/24.
    • Bidding process is substantially complete – three main bid packages
    • Soft mobilization has commenced to demolish buildings (per approved demo permit) and prepare site for anticipated building permit.
    • BRIC (Design Team) continues to get as much student engagement as possible during the key design milestones.
    • Pence (General Contractor) has hired short-term interns from DDHS to assist with onsite project administration. Additional student engagement is also under review.

DDHS North Building

ArchitectSoderstrom Architects
Contractor (CMGC)Pence Contractors
Project Budgeton budget
Project Scheduleon Schedule
PermitApproved
ConstructionSummer 2024
Move InFall 2024
  • Current Project Status:
    • Repair/Renovation scopes are ongoing, currently no concerns with finishing scopes of work over the summer schedule.
    • Initial budgeted work came in under budget however the district had an alternate bid for bleacher replacement. Being that the project came in under budget, the CORE team recommended to the board to replaced, rather than refurbish the bleachers, which they approved. This added scope will be funded through project savings and bleachers scope will be completed summer 2025.
    • Ongoing Bi-weekly meetings with staff to coordinate, communicate summer construction activities continue.

Project Photos 

Current Construction Timeline

DDHS CTE

ArchitectBRIC Architects
Contractor (CMGC)Pence Contractors
Project Budgeton budget
Project Scheduleon Schedule
DesignMay 2023 – March 2024
PermitNovember 2023 – June 2024
BiddingDecember 2023 – March 2024
ConstructionApril 2024 – August 2025
Owner Move InFall 2025
  • Current Project Status:
    • Building Permit was submitted to City of Portland on 1/19/24.
    • Bidding process is substantially complete – three main bid packages
    • Soft mobilization is commencing middle of May
    • Working with DDSD communications team to coordinate groundbreaking event, scheduled for May 4, 2024.
    • BRIC (Design Team) continues to get as much student engagement as possible during the key design milestones.
    • Pence (General Contractor) is in the process of hiring short- and long-term interns from DDHS to assist with onsite project administration. Additional student engagement is also under review.

DDHS North Building

ArchitectSoderstrom Architects
Contractor (CMGC)Pence Contractors
Project Budgeton budget
Project Scheduleon Schedule
DesignN/A
PermitNovember 2023 – March 2024
BiddingNovember 2023 – March 2024
ConstructionApril 2024 – August 2025
Owner Move InFall 2024
  • Current Project Status:
    • Initial budgeted work came in under budget however the district had an alternate bid for bleacher replacement. Being that the project came in under budget, the CORE team recommended to the board to replaced, rather than refurbish the bleachers, which they approved. This added scope will be funded through project savings and bleachers scope will be completed summer 2025.
    • Ongoing Bi-weekly meetings with staff to coordinate, communicate and prepare for summer construction continue.

North Campus Secured Vestibule Renderings

Proposed Secured Vestibule (North Campus) Renderings

CTE Symbolic Groundbreaking Ceremony

On May 4, we hosted our symbolic groundbreaking ceremony for our future new CTE building. We want to thank everyone who attended this important event, especially our student and parent speakers, who shared how vital this new CTE building is to our community. For those who could not make it or wish to relive the moment, please watch the highlight video below.

All Educational Facility Sites: Intercom & Clocks

ArchitectLandis Consulting
Contractor (CMGC)GB Manchester. The Electrical Contractor
Project Budgeton budget
Project Scheduleon Schedule
DesignJanuary 2024 – March 2026
BiddingApril 2024
ConstructionSummer 2024 – Summer 2026 (Multiple Summers)
  • Current Project Status:
    • Finalized standards with DDSD stakeholders
    • Targeting to complete DDHS North Campus and AOMS summer 2024.
    • Working with DDSD, design team, and GB Manchester to determine the capacities of work that can be completed over the future summers and priorities with DDSD stakeholders accordingly.

DDHS CTE

DesignFinal Stages
BiddingOngoing
PermitSubmitted and under review with City of Portland
General ContractorPence
Pre-ConstructionOngoing with general contractor
Bi-Weekly MeetingsTBD
  • Construction scheduled to commence April 2024 and be substantially completed in July 2025
  • Target opening date: fall of 2025

DDHS North Building

DesignComplete
BiddingComplete
PermitSubmitted and under review with City of Portland
General ContractorPence
Pre-ConstructionOngoing with general contractor
Bi-Weekly MeetingsTBD
  • Construction scheduled to commence June 2024 and be substantially completed in August 2024
  • Target Completion date: August 2024

All Educational Facility Sites: Intercom & Clocks

  • Construction is scheduled to commence in June 2024 and be substantially completed in July 2026. This scope will be at all educational facilities and will be completed over the next three summers. 
  • Target Completion date: Fall of 2024
  • Finalizing standards with DDSD stakeholders and the design teams.
DesignOngoing
BiddingOngoing