Land Use Permit started with City of Portland on Summer 2023.
Building Permit was submitted to City of Portland on 1/19/24.
Bidding process is substantially complete – three main bid packages
Soft mobilization has commenced to demolish buildings (per approved demo permit) and prepare site for anticipated building permit.
BRIC (Design Team) continues to get as much student engagement as possible during the key design milestones.
Pence (General Contractor) has hired short-term interns from DDHS to assist with onsite project administration. Additional student engagement is also under review.
DDHS North Building
Architect
Soderstrom Architects
Contractor (CMGC)
Pence Contractors
Project Budget
on budget
Project Schedule
on Schedule
Permit
Approved
Construction
Summer 2024
Move In
Fall 2024
Current Project Status:
Repair/Renovation scopes are ongoing, currently no concerns with finishing scopes of work over the summer schedule.
Initial budgeted work came in under budget however the district had an alternate bid for bleacher replacement. Being that the project came in under budget, the CORE team recommended to the board to replaced, rather than refurbish the bleachers, which they approved. This added scope will be funded through project savings and bleachers scope will be completed summer 2025.
Ongoing Bi-weekly meetings with staff to coordinate, communicate summer construction activities continue.
Building Permit was submitted to City of Portland on 1/19/24.
Bidding process is substantially complete – three main bid packages
Soft mobilization is commencing middle of May
Working with DDSD communications team to coordinate groundbreaking event, scheduled for May 4, 2024.
BRIC (Design Team) continues to get as much student engagement as possible during the key design milestones.
Pence (General Contractor) is in the process of hiring short- and long-term interns from DDHS to assist with onsite project administration. Additional student engagement is also under review.
DDHS North Building
Architect
Soderstrom Architects
Contractor (CMGC)
Pence Contractors
Project Budget
on budget
Project Schedule
on Schedule
Design
N/A
Permit
November 2023 – March 2024
Bidding
November 2023 – March 2024
Construction
April 2024 – August 2025
Owner Move In
Fall 2024
Current Project Status:
Initial budgeted work came in under budget however the district had an alternate bid for bleacher replacement. Being that the project came in under budget, the CORE team recommended to the board to replaced, rather than refurbish the bleachers, which they approved. This added scope will be funded through project savings and bleachers scope will be completed summer 2025.
Ongoing Bi-weekly meetings with staff to coordinate, communicate and prepare for summer construction continue.
North Campus Secured Vestibule Renderings
CTE Symbolic Groundbreaking Ceremony
On May 4, we hosted our symbolic groundbreaking ceremony for our future new CTE building. We want to thank everyone who attended this important event, especially our student and parent speakers, who shared how vital this new CTE building is to our community. For those who could not make it or wish to relive the moment, please watch the highlight video below.
All Educational Facility Sites: Intercom & Clocks
Architect
Landis Consulting
Contractor (CMGC)
GB Manchester. The Electrical Contractor
Project Budget
on budget
Project Schedule
on Schedule
Design
January 2024 – March 2026
Bidding
April 2024
Construction
Summer 2024 – Summer 2026 (Multiple Summers)
Current Project Status:
Finalized standards with DDSD stakeholders
Targeting to complete DDHS North Campus and AOMS summer 2024.
Working with DDSD, design team, and GB Manchester to determine the capacities of work that can be completed over the future summers and priorities with DDSD stakeholders accordingly.
Construction scheduled to commence April 2024 and be substantially completed in July 2025
Target opening date: fall of 2025
DDHS North Building
Design
Complete
Bidding
Complete
Permit
Submitted and under review with City of Portland
General Contractor
Pence
Pre-Construction
Ongoing with general contractor
Bi-Weekly Meetings
TBD
Construction scheduled to commence June 2024 and be substantially completed in August 2024
Target Completion date: August 2024
All Educational Facility Sites: Intercom & Clocks
Construction is scheduled to commence in June 2024 and be substantially completed in July 2026. This scope will be at all educational facilities and will be completed over the next three summers.
Target Completion date: Fall of 2024
Finalizing standards with DDSD stakeholders and the design teams.