David Douglas High School Bond Updates
Project Scope Summary
| Priority 1 Project | Amount | Start & End Date |
|---|---|---|
| Future Careers Building | 46,300,000 | 2023 – Fall 2025 |
| DDHS Renovations | Amount | Start & End Date |
|---|---|---|
| Replace lighting for football and baseball fields | 3,600,000 | Feb. 2025 – Dec. 2026 |
| DDHS North Renovations | Amount | Start & End Date |
|---|---|---|
| Replace existing generator and add additional emergency | 11,300,000 | 2023 – Dec. 2024 |
| Replace Sprayed on ceiling finishes in north building | ||
| Replace north building drive system on bleachers | ||
| Partial replacement of roofing on north building | ||
| Replace some of domestic water supply in north building | ||
| Replace a portion of sewer at north building | ||
| Remodel entry for a secure vestibule |
| DDHS South Renovations | Amount | Start & End Date |
|---|---|---|
| Replace fire alarm system in south building | 13,150,000 | Jan. 2024 – Dec. 2025 |
| Remodel main entry area in south building | ||
| Replace part of roof on south building and part of PAC | ||
| Replace some of domestic water supply line in south building | ||
| Replace damaged roof structure |
| DDHS PAC Renovations | Amount | Start & End Date |
|---|---|---|
| Upgrade some theatre lighting at PAC | 1,390,000 | Feb. 2025–Dec. 2026 |
| Upgrade some theater systems at PAC |
| Aquatic Center Renovations | Amount | Start & End Date |
|---|---|---|
| Replace 5 Tier Bleachers | 150,000 | Feb. 2025–Dec. 2026 |
| Add nonslip texture to pool deck | ||
| Upgrade Intercom Systems & Some Clock Systems (All Educational Facility Sites) | 8,005,000 | July 2023–December 2026 |
October 2025
Latest Look Inside the South Building
Current Project Status (South Building)
- Remodeled main entry area (safety vestibule)
- Replaced the fire alarm system
- Replaced part of the roof on the south campus and part of the Performing Arts Center (PAC)
- Replaced the damaged roof structure
- Replaced lighting for football and baseball fields
Latest Look Inside the North Building

Current Project Status (North Building)
- Replaced the North Gym bleachers
- Replaced the drive system on the North Gym bleachers
Latest Look Inside the Aquatics Center

Current Project Status (Aquatics Center)
- Replaced 5 tier bleachers
Before and After Photos of the CTE
November 2024

Latest Photos







Current Project Status (CTE)
- On budget and on schedule
- Status: to be substantially completed by December 2025
June 2025
Current Construction Timeline
DDHS
| Architect | BRIC Architects |
| Contractor (CMGC) | Pence Contractors |
| Project Budget | on budget |
| Project Schedule | Revised Schedule due to permitting issues approved |
| Design | May 2023 – March 2024 |
| Permit | November 2023 – June 2024 |
| Bidding | December 2023 – March 2024 |
| Construction | April 2024 – December 2025 |
| Move In | Winter Break 2025 |
| Architect | Soderstrom Architects |
| Contractor (CMGC) | Pence Contractors |
| Project Budget | on budget |
| Project Schedule | on Schedule |
| Permit | Approved |
| Construction | Summer 2025 |
| Move In | Fall 2025 |
- Current Project Status:
- Lighting installation is underway on the athletic fields.
- The construction is to begin on the South Building.
- The new pool bleachers have arrived and are scheduled for installation at a later date.
- The South Campus and Pool/Aquatics Center Building are closed this summer.
- Current Project Status:
- CTE Center so far is going as planned.
- In process of getting quotes for the ambulance simulator and the automotive lifts.
May 2025
Current Construction Timeline
DDHS CTE
| Architect | BRIC Architects |
| Contractor (CMGC) | Pence Contractors |
| Project Budget | on budget |
| Project Schedule | Revised Schedule due to permitting issues approved |
| Design | May 2023 – March 2024 |
| Permit | November 2023 – June 2024 |
| Bidding | December 2023 – March 2024 |
| Construction | April 2024 – December 2025 |
| Move In | Winter Break 2025 |
- Current Project Status:
- Bidding process complete – three main bid packages
- Construction – The roof and exterior walls/ windows is in process. Interior Walls are framed. Full dry-in will allow final wall finishes to start this month.
- Pence has had 2 student interns on staff. They expect to continue with them for the
duration of construction. - Pence meets with the principals every other week to coordinate construction activities with the school.
DDHS
| Architect | Soderstrom Architects |
| Contractor (CMGC) | Pence Contractors |
| Project Budget | on budget |
| Project Schedule | on Schedule |
| Permit | Approved |
| Construction | Summer 2025 |
| Move In | Fall 2025 |
- Current Project Status:
- Final cost awarded to Pence.
- Ongoing Bi-weekly meetings with staff to coordinate, communicate
and prepare for summer construction continue. - Bleachers in North Gym will require substantial structural improvements this summer to meet current codes.
Photos coming soon.
February 2025
DDHS CTE
| Architect | BRIC Architects |
| Contractor (CMGC) | Pence Contractors |
| Project Budget | on budget |
| Project Schedule | Revised Schedule due to permitting issues approved |
| Design | May 2023 – March 2024 |
| Permit | November 2023 – June 2024 |
| Bidding | December 2023 – March 2024 |
| Construction | April 2024 – December 2025 |
| Move In | Winter Break 2025 |
- Current Project Status:
- Building Permit Approved.
- Bidding process complete – three main bid packages.
- Construction – The wood ceiling structure is nearing completion. The next focus will be the concrete slabs.
- Pence has had 2 student interns on staff. They expect to continue with them for the duration of construction.
- Pence meets with the principals every other week to coordinate construction activities with the school.
- CTE Topping Off Ceremony went well
DDHS
| Architect | Soderstrom Architects |
| Contractor (CMGC) | Pence Contractors |
| Project Budget | on budget |
| Project Schedule | on Schedule |
| Permit | Approved |
| Construction | Summer 2025 |
| Move In | Fall 2025 |
- Current Project Status:
- Final cost awarded to Pence.
- Ongoing Bi-weekly meetings with staff to coordinate, communicate and prepare for summer construction continue.
- Move Plan is completed.
- Some work in Aquatics to be done during Spring Break to minimize Summer interruptions.
- Bleachers in North Gym will require substantial structural improvements this summer to meet current codes.
CTE Topping Off Ceremony
On January 31st, we held a CTE “Topping Off” Ceremony with our administrators, students, workers, architects, and other individuals who have been directly involved with the construction of the CTE building.
Board members, admin, and CTE students were able to walk in the construction site to see the progress.
The summer work will include final sidewalks, canopies and landscaping. Fall work will be interior finishes.




Project Photos





January 2025
Project Updates
Career Technical Education Center:
Work is continuing on the CTE Center. The summer work will include final sidewalks, canopies and
landscaping. Fall work will be interior finishes.
North High School Renovations:
We have a few renovations happening over the summer including replacing the parking lot driveways and
expanding plantings in the parking lots. These are all nonconforming conditions required due to the new
CTE center. We also planned on replacing the gym bleachers this summer. These may need some
additional reinforcement so we are continuing some discussion on whether this will be needed and what
the cost, if any, would be.
South High School Renovations:
There will be quite a bit of work this summer at the South building. The building is having the roof
replaced, a new water distribution pipe installed, a new fire alarm and intercom system installed, a new
front entry/secure vestibule at the south, renovations to the metals, pottery shed and renovations for
where the print shop will go and the early education program. The main entry driveways will be replaced
due to nonconforming requirements, the walk-in cooler will be replaced, and the air conditioning in the
board room will be replaced. South building will not be available for use during the summer, and we will
need to move Board meetings.
The Football field and baseball field lights will be replaced and intercoms will be added. The old auto shop, greenhouse, and greenhouse classrooms are slated for demolition January 2026.
PAC:
We are replacing the theater roofing and some HVAC ductwork that tied into the roofing. The theater
lights and sound systems will be replaced. A new pathway will be added around the bus loop as part of
the nonconforming conditions for the CTE Center.
Aquatics Center:
Work for this summer includes replacing the north bleachers and will look like the south bleachers, adding an epoxy coating with a nonslip texture which will need to be redone about every 10-15 years. Additional plantings are required as part of the CTE nonconforming conditions. We anticipate the pool to be closed 7-8 weeks to accommodate the work needing to be completed.
December 2024
Project Updates
Career Technical Education Center:
Walls are up where the auto shop will be. Everything is moving along, and the plan for move-in in December 2025 is still on track.
Watch the CTE Building Time Lapse Video
North High School Renovations:
Open punchlist items include vestibule glass detailing to be addressed over winter break and heat exchanger removal from the boiler room done by the end of December. There are a couple additional items regarding vestibule acoustics and ventilation that we will be addressing. Some settling where the sewer line was replaced will be addressed in the spring when the ground is drier.
High School South Renovations:
This includes upgrades to stadium and baseball field lighting as well as renovations to the South Building. The North High School bleacher replacement and pool bleacher replacements are also planned for next summer.
November 2024
DDHS CTE
| Architect | BRIC Architects |
| Contractor (CMGC) | Pence Contractors |
| Project Budget | on budget |
| Project Schedule | Behind Target Schedule due to permitting issues |
| Design | May 2023 – March 2024 |
| Permit | November 2023 – June 2024 |
| Bidding | December 2023 – March 2024 |
| Construction | April 2024 – December 2025 |
| Move In | Winter Break 2025 |
- Current Project Status:
- Building Permit Approved.
- Bidding process complete – three main bid packages.
- Construction Masonry wall construction at Auto Shop ongoing and structural steel on schedule to commence middle of November.
- BRIC and Pence participated in Back to School Open House. The team will continue to reach out for student engagement as possible during the construction process.
- R&C/Pence meets with the principals every other week to coordinate construction activities with the school.
- Note photos of Pence’s signage to prevent worker /student interactions, especially during class changes.
DDHS North Building
| Architect | Soderstrom Architects |
| Contractor (CMGC) | Pence Contractors |
| Project Budget | on budget |
| Project Schedule | on Schedule |
| Permit | Approved |
| Construction | Summer 2024 |
| Move In | Fall 2024 |
- Current Project Status:
- Project is substantially complete, and team is working on punch list items and project closeout items.
DDHS South Building
| Architect | Soderstrom Architects |
| Contractor (CMGC) | Pence Contractors |
| Project Budget | on budget |
| Project Schedule | on Schedule |
| Permit | Approved |
| Construction | Summer 2025 |
| Move In | Fall 2025 |
- Current Project Status:
- Final cost awarded to Pence.
- Ongoing Bi-weekly meetings with staff to coordinate, communicate and prepare for summer construction continue.
Project Photos



Project Video
October 2024
Dear David Douglas High School Families,
We would like to extend our heartfelt gratitude once again to all of you who voted in support of the 2022 Bond Measure for the David Douglas School District. Your continued commitment has made it possible for us to enhance our facilities and provide even better opportunities for our students.
Throughout the summer, our high school has been bustling with construction and renovations in preparation for the upcoming school year. We’re excited to share some of the key improvements:
- North Campus Roofing: The roof on our North Campus has been completely replaced, ensuring a safer and more durable structure for years to come.
- North Campus Gym: Our gym has undergone significant renovations, and we are thrilled with how it has turned out. It’s now ready to serve our students and community well.
- New Security Vestibule: As part of our commitment to student safety, we have updated our security vestibule to enhance safety measures at the main entrance of the school. This will further protect students, staff, and visitors by improving controlled access to the building.
- New CTE Building: Construction on our brand-new Career and Technical Education (CTE) building began earlier this summer. This exciting addition will continue to take shape throughout the school year and, once completed, will offer expanded hands-on learning opportunities in various career fields.
We are incredibly excited about what the future holds and are grateful for your unwavering support. Without your dedication and partnership, these improvements and new facilities would not be possible. Together, we are building a brighter future for our students and the entire community.
Thank you once again for helping us take this important step forward.
Sincerely,
David Douglas High School
Here are some before and after photos of the bond construction.
Please enjoy our DDHS Bond Update Youtube Video.
August 2024
DDHS CTE
| Architect | BRIC Architects |
| Contractor (CMGC) | Pence Contractors |
| Project Budget | on budget |
| Project Schedule | Behind Target Schedule due to permitting issues |
| Design | May 2023 – March 2024 |
| Permit | November 2023 – June 2024 |
| Bidding | December 2023 – March 2024 |
| Construction | April 2024 – August 2025 |
| Move In | Fall / Winter 2025 |
- Current Project Status:
- Land Use Permit started with City of Portland on Summer 2023.
- Building Permit was submitted to City of Portland on 1/19/24.
- Bidding process is substantially complete – three main bid packages
- Soft mobilization has commenced to demolish buildings (per approved demo permit) and prepare site for anticipated building permit.
- BRIC (Design Team) continues to get as much student engagement as possible during the key design milestones.
- Pence (General Contractor) has hired short-term interns from DDHS to assist with onsite project administration. Additional student engagement is also under review.
DDHS North Building
| Architect | Soderstrom Architects |
| Contractor (CMGC) | Pence Contractors |
| Project Budget | on budget |
| Project Schedule | on Schedule |
| Permit | Approved |
| Construction | Summer 2024 |
| Move In | Fall 2024 |
- Current Project Status:
- Repair/Renovation scopes are ongoing, currently no concerns with finishing scopes of work over the summer schedule.
- Initial budgeted work came in under budget however the district had an alternate bid for bleacher replacement. Being that the project came in under budget, the CORE team recommended to the board to replaced, rather than refurbish the bleachers, which they approved. This added scope will be funded through project savings and bleachers scope will be completed summer 2025.
- Ongoing Bi-weekly meetings with staff to coordinate, communicate summer construction activities continue.
Project Photos



May 2024
DDHS CTE
| Architect | BRIC Architects |
| Contractor (CMGC) | Pence Contractors |
| Project Budget | on budget |
| Project Schedule | on Schedule |
| Design | May 2023 – March 2024 |
| Permit | November 2023 – June 2024 |
| Bidding | December 2023 – March 2024 |
| Construction | April 2024 – August 2025 |
| Owner Move In | Fall 2025 |
- Current Project Status:
- Building Permit was submitted to City of Portland on 1/19/24.
- Bidding process is substantially complete – three main bid packages
- Soft mobilization is commencing middle of May
- Working with DDSD communications team to coordinate groundbreaking event, scheduled for May 4, 2024.
- BRIC (Design Team) continues to get as much student engagement as possible during the key design milestones.
- Pence (General Contractor) is in the process of hiring short- and long-term interns from DDHS to assist with onsite project administration. Additional student engagement is also under review.
DDHS North Building
| Architect | Soderstrom Architects |
| Contractor (CMGC) | Pence Contractors |
| Project Budget | on budget |
| Project Schedule | on Schedule |
| Design | N/A |
| Permit | November 2023 – March 2024 |
| Bidding | November 2023 – March 2024 |
| Construction | April 2024 – August 2025 |
| Owner Move In | Fall 2024 |
- Current Project Status:
- Initial budgeted work came in under budget however the district had an alternate bid for bleacher replacement. Being that the project came in under budget, the CORE team recommended to the board to replaced, rather than refurbish the bleachers, which they approved. This added scope will be funded through project savings and bleachers scope will be completed summer 2025.
- Ongoing Bi-weekly meetings with staff to coordinate, communicate and prepare for summer construction continue.
North Campus Secured Vestibule Renderings

CTE Symbolic Groundbreaking Ceremony
On May 4, we hosted our symbolic groundbreaking ceremony for our future new CTE building. We want to thank everyone who attended this important event, especially our student and parent speakers, who shared how vital this new CTE building is to our community. For those who could not make it or wish to relive the moment, please watch the highlight video below.
All Educational Facility Sites: Intercom & Clocks
| Architect | Landis Consulting |
| Contractor (CMGC) | GB Manchester. The Electrical Contractor |
| Project Budget | on budget |
| Project Schedule | on Schedule |
| Design | January 2024 – March 2026 |
| Bidding | April 2024 |
| Construction | Summer 2024 – Summer 2026 (Multiple Summers) |
- Current Project Status:
- Finalized standards with DDSD stakeholders
- Targeting to complete DDHS North Campus and AOMS summer 2024.
- Working with DDSD, design team, and GB Manchester to determine the capacities of work that can be completed over the future summers and priorities with DDSD stakeholders accordingly.
February 2024
DDHS CTE
| Design | Final Stages |
| Bidding | Ongoing |
| Permit | Submitted and under review with City of Portland |
| General Contractor | Pence |
| Pre-Construction | Ongoing with general contractor |
| Bi-Weekly Meetings | TBD |
- Construction scheduled to commence April 2024 and be substantially completed in July 2025
- Target opening date: fall of 2025
DDHS North Building
| Design | Complete |
| Bidding | Complete |
| Permit | Submitted and under review with City of Portland |
| General Contractor | Pence |
| Pre-Construction | Ongoing with general contractor |
| Bi-Weekly Meetings | TBD |
- Construction scheduled to commence June 2024 and be substantially completed in August 2024
- Target Completion date: August 2024
All Educational Facility Sites: Intercom & Clocks
- Construction is scheduled to commence in June 2024 and be substantially completed in July 2026. This scope will be at all educational facilities and will be completed over the next three summers.
- Target Completion date: Fall of 2024
- Finalizing standards with DDSD stakeholders and the design teams.
| Design | Ongoing |
| Bidding | Ongoing |