Earl Boyles Elementary School Bond Updates

Project Scope Summary

RenovationsAmountStart & End Date
Replace exterior cedar siding that has failed1,500,000Dec. 2024–Dec. 2025
Reroof portion of the building
Remodel entry for a secure vestibule
Upgrade Intercom Systems & Some Clock Systems (All Educational Facility Sites)8,005,000July 2023–December 2026

Current Construction Timeline

All Educational Facility Sites: Intercom & Clocks

  • Construction is scheduled to commence in June 2024 and be substantially completed in July 2026. This scope will be at all educational facilities and will be completed over the next three summers. 
  • Target Completion date: Fall of 2024
  • Finalizing standards with DDSD stakeholders and the design teams.
DesignOngoing
BiddingOngoing