Fir Ridge Campus Bond Updates

Project Scope Summary

RenovationsAmountStart & End Date
Replace roofing1,525,000Feb. 2025 – Dec. 2026
Remodel entry for a secure vestibule
Upgrade Intercom Systems & Some Clock Systems (All Educational Facility Sites)8,005,000July 2023 – December 2026

Current Construction Timeline

ArchitectAXIS Design
ContractorTBD – Bid to prequalified GC’s
Project Budgeton budget
Project Scheduleon Schedule
Pre-Design/ProgrammingMarch 2024 – July 2024
DesignJuly 2024 – December 2024
PermitNovember 2024 – March 2025
BiddingJanuary 2024
ConstructionSummer 2025
Move Back InFall 2025
  • Current Project Status –
    • Pre-design/programming is underway
    • Goal is to impact the staff/student as little as possible
ArchitectAXIS Design
ContractorTBD – Bid to prequalified GC’s
Project Budgeton budget
Project Scheduleon Schedule
Pre-Design/ProgrammingJanuary 2024 – February 2024
DesignMarch 2024 – November 2024
PermitNovember 2024 – March 2025
BiddingNovember 2024
ConstructionSummer 2025
Owner Move Back InFall 2025
  • Current Project Status –
    • Finished up the predesign phase and proceeding into Design phase
    • Goal is to impact the staff/student as least as possible

All Educational Facility Sites: Intercom & Clocks

ArchitectLandis Consulting
Contractor (CMGC)GB Manchester. The Electrical Contractor
Project Budgeton budget
Project Scheduleon Schedule
DesignJanuary 2024 – March 2026
BiddingApril 2024
ConstructionSummer 2024 – Summer 2026 (Multiple Summers)

All Educational Facility Sites: Intercom & Clocks

  • Construction is scheduled to commence in June 2024 and be substantially completed in July 2026. This scope will be at all educational facilities and will be completed over the next three summers. 
  • Target Completion date: Fall of 2024
  • Finalizing standards with DDSD stakeholders and the design teams.
DesignOngoing
BiddingOngoing