Fir Ridge Campus Bond Updates

Project Scope Summary

RenovationsAmountStart & End Date
Replace roofing1,525,000Feb. 2025 – Dec. 2026
Remodel entry for a secure vestibule
Upgrade Intercom Systems & Some Clock Systems (All Educational Facility Sites)8,005,000July 2023 – December 2026

Latest Look Inside the Building

People gathered in a school hallway near glass doors, with a floor cleaning machine visible on the side.

Current Project Status

  • Remodeled entry and a secure vestibule
  • Replaced roofing 

Current Construction Timeline

ArchitectAXIS Design
ContractorBrockamp & Jaeger
ConstructionUnderway, Substantial Completion by August 22nd

Current Project Status

  • Permit has been issued.
  • Contractor has mobilized to site.
  • Project is currently on schedule.
  • Still completing work on the safety vestibule. Please note that the door may not be installed by the 25th.

Current Construction Timeline

ArchitectAXIS Design
ContractorBrockamp & Jaeger
ConstructionSummer 2025

Current Project Status

  • The shipment date for the sound-rated bathroom doors required by the permit has been delayed. These doors are now expected to arrive in the first or second week of September.
  • The campus will be closed for the summer. 

Current Construction Timeline

ArchitectAXIS Design
ContractorBrockamp & Jaeger
ConstructionSummer 2025

Current Project Status

  • Team is actively working through any long-lead procurement items.
  • Permit has been issued.
  • Contractor will mobilize to the site on June 16, 2025.
  • Goal is to impact the staff/student as least as possible
ArchitectAXIS Design
ContractorTBD – Bid to prequalified GC’s
Project ScheduleOn Schedule
DesignComplete
PermitUnder Review with City of Portland
BiddingDue February 2025
ConstructionSummer 2025

Project Updates

Fir Ridge is currently out to bid.

Project Updates

Axis Design Group is currently working on the plans for the roof replacement, secure vestibule, and bike racks that will be required. Construction design is at 75%, and the cost estimate is within budget at this time.

ArchitectAXIS Design
ContractorTBD – Bid to prequalified GC’s
Project Budgeton budget
Project Scheduleon Schedule
Pre-Design/ProgrammingMarch 2024 – July 2024
DesignJuly 2024 – December 2024
PermitNovember 2024 – March 2025
BiddingJanuary 2025
ConstructionSummer 2025
Move Back InFall 2025
  • Current Project Status:
    • Pre-design/programming is complete. 
    • The design process is underway. 
    • The goal is to impact the staff/student as little as possible.
ArchitectAXIS Design
ContractorTBD – Bid to prequalified GC’s
Project Budgeton budget
Project Scheduleon Schedule
Pre-Design/ProgrammingMarch 2024 – July 2024
DesignJuly 2024 – December 2024
PermitNovember 2024 – March 2025
BiddingJanuary 2025
ConstructionSummer 2025
Move Back InFall 2025
  • Current Project Status –
    • Pre-design/programming is underway
    • Goal is to impact the staff/student as little as possible
ArchitectAXIS Design
ContractorTBD – Bid to prequalified GC’s
Project Budgeton budget
Project Scheduleon Schedule
Pre-Design/ProgrammingJanuary 2024 – February 2024
DesignMarch 2024 – November 2024
PermitNovember 2024 – March 2025
BiddingNovember 2024
ConstructionSummer 2025
Owner Move Back InFall 2025
  • Current Project Status –
    • Finished up the predesign phase and proceeding into Design phase
    • Goal is to impact the staff/student as least as possible

All Educational Facility Sites: Intercom & Clocks

ArchitectLandis Consulting
Contractor (CMGC)GB Manchester. The Electrical Contractor
Project Budgeton budget
Project Scheduleon Schedule
DesignJanuary 2024 – March 2026
BiddingApril 2024
ConstructionSummer 2024 – Summer 2026 (Multiple Summers)

All Educational Facility Sites: Intercom & Clocks

  • Construction is scheduled to commence in June 2024 and be substantially completed in July 2026. This scope will be at all educational facilities and will be completed over the next three summers. 
  • Target Completion date: Fall of 2024
  • Finalizing standards with DDSD stakeholders and the design teams.
DesignOngoing
BiddingOngoing