Upgrade Intercom Systems & Some Clock Systems (All Educational Facility Sites)
8,005,000
July 2023 – December 2026
October 2025
Latest Look Inside the Building
Current Project Status
Remodeled entry and a secure vestibule
Replaced roofing
July 2025
Current Construction Timeline
Architect
AXIS Design
Contractor
Brockamp & Jaeger
Construction
Underway, Substantial Completion by August 22nd
Current Project Status
Permit has been issued.
Contractor has mobilized to site.
Project is currently on schedule.
Still completing work on the safety vestibule. Please note that the door may not be installed by the 25th.
June 2025
Current Construction Timeline
Architect
AXIS Design
Contractor
Brockamp & Jaeger
Construction
Summer 2025
Current Project Status
The shipment date for the sound-rated bathroom doors required by the permit has been delayed. These doors are now expected to arrive in the first or second week of September.
The campus will be closed for the summer.
May 2025
Current Construction Timeline
Architect
AXIS Design
Contractor
Brockamp & Jaeger
Construction
Summer 2025
Current Project Status
Team is actively working through any long-lead procurement items.
Permit has been issued.
Contractor will mobilize to the site on June 16, 2025.
Goal is to impact the staff/student as least as possible
February 2025
Architect
AXIS Design
Contractor
TBD – Bid to prequalified GC’s
Project Schedule
On Schedule
Design
Complete
Permit
Under Review with City of Portland
Bidding
Due February 2025
Construction
Summer 2025
January 2025
Project Updates
Fir Ridge is currently out to bid.
December 2024
Project Updates
Axis Design Group is currently working on the plans for the roof replacement, secure vestibule, and bike racks that will be required. Construction design is at 75%, and the cost estimate is within budget at this time.
November 2024
Architect
AXIS Design
Contractor
TBD – Bid to prequalified GC’s
Project Budget
on budget
Project Schedule
on Schedule
Pre-Design/Programming
March 2024 – July 2024
Design
July 2024 – December 2024
Permit
November 2024 – March 2025
Bidding
January 2025
Construction
Summer 2025
Move Back In
Fall 2025
Current Project Status:
Pre-design/programming is complete.
The design process is underway.
The goal is to impact the staff/student as little as possible.
August 2024
Architect
AXIS Design
Contractor
TBD – Bid to prequalified GC’s
Project Budget
on budget
Project Schedule
on Schedule
Pre-Design/Programming
March 2024 – July 2024
Design
July 2024 – December 2024
Permit
November 2024 – March 2025
Bidding
January 2025
Construction
Summer 2025
Move Back In
Fall 2025
Current Project Status –
Pre-design/programming is underway
Goal is to impact the staff/student as little as possible
May 2024
Architect
AXIS Design
Contractor
TBD – Bid to prequalified GC’s
Project Budget
on budget
Project Schedule
on Schedule
Pre-Design/Programming
January 2024 – February 2024
Design
March 2024 – November 2024
Permit
November 2024 – March 2025
Bidding
November 2024
Construction
Summer 2025
Owner Move Back In
Fall 2025
Current Project Status –
Finished up the predesign phase and proceeding into Design phase
Goal is to impact the staff/student as least as possible
All Educational Facility Sites: Intercom & Clocks
Architect
Landis Consulting
Contractor (CMGC)
GB Manchester. The Electrical Contractor
Project Budget
on budget
Project Schedule
on Schedule
Design
January 2024 – March 2026
Bidding
April 2024
Construction
Summer 2024 – Summer 2026 (Multiple Summers)
February 2024
All Educational Facility Sites: Intercom & Clocks
Construction is scheduled to commence in June 2024 and be substantially completed in July 2026. This scope will be at all educational facilities and will be completed over the next three summers.
Target Completion date: Fall of 2024
Finalizing standards with DDSD stakeholders and the design teams.