Floyd Light Middle School Bond Updates

Project Scope Summary

RenovationsAmountStart & End Date
Install generator and service lines7,000,000Feb. 2024 – Dec. 2025
Upgrade building HVAC System
Remodel entry for a secure vestibule
Repair/ Replace Track Surface (Alice Ott, Floyd Light & Ron Russell)1,250,000July 2023 – Dec. 2024
Upgrade Intercom Systems & Some Clock Systems (All Educational Facility Sites)8,005,000July 2023 – December 2026

Construction Progress Photos

Before

After

Exterior view of a school building with a covered walkway, blue posts and trim, a ramp with railings.

Current Project Status

  • Remodeled entry for a secure vestibule 
  • Installed generator and service lines
  • Updated building HVAC system 

Current Construction Timeline

ArchitectBBL Architects
Contractor (CMGC)Howard S. Wright
ConstructionOn Schedule to construct over summer 2025

Current Project Status

  • Permit has been issued.
  • Contractor has mobilized to site.
  • Early May mobilization to site has benefitted overall project schedule.
  • Project is currently on schedule.
  • Project will not require a second phase for cooling due to capacity of existing electrical systems.

Current Construction Timeline

ArchitectBBL Architects
Contractor (CMGC)Howard S. Wright
ConstructionSummer 2025

Current Project Status

  • Staff are currently packing and preparing for the move, and everything is progressing according to schedule.
  • The school building will be closed for the summer. 

Current Construction Timeline

ArchitectBBL Architects
Contractor (CMGC)Howard S. Wright
ConstructionSummer 2025


Current Project Status

  • Permit has been issued.
  • Contractor will mobilize to the site on June 16, 2025.
  • Early exterior work will begin in May to ensure successful project completion.
  • GMP has been established.
  • Project will not require a second phase for cooling due to capacity of existing
    electrical systems.
ArchitectBBL Architects
Contractor (CMGC)Howard S. Wright
Project ScheduleOn Schedule
DesignComplete
PermitIssued
ConstructionSummer 2025
Move Back InFall 2025
  • Current Project Status:
    • Long lead buyout is complete. 
    • Buyout for all remaining divisions is 95% complete, initial GMP is at/under budget. 
    • Goal is to impact the staff/student as least as possible.
    • Project will not require a second phase for cooling due to capacity of existing electrical systems. 
ArchitectBBL Architects
Contractor (CMGC)Howard S. Wright
Project Budgeton budget
Project Scheduleon Schedule
Pre-Design/ProgrammingNovember 2023 – January 2024
DesignJanuary 2024 – November 2024
PermitNovember 2024 – March 2025
BiddingJune 2024 – November 2024
ConstructionSummer 2025
Move Back InFall 2025
  • Current Project Status:
    • DD (Design Development) phase is complete.
    • Team is working towards completion of 100% CD (Construction Document) set.
    • Selected Howard S. Wright through an RFP process for CMGC services.
    • Target of middle of June 2024 was met, to bid out all long lead items with the CMGC contractor, then bid all the remaining scopes out in November 2024. 
    • Goal is to impact the staff/student as little as possible.
ArchitectBBL Architects
Contractor (CMGC)Howard S. Wright
Project Budgeton budget
Project Scheduleon Schedule
Pre-Design/ProgrammingNovember 2023 – January 2024
DesignJanuary 2024 – November 2024
PermitNovember 2024 – March 2025
BiddingJune 2024 – November 2024
ConstructionSummer 2025
Owner Move Back InFall 2025
  • Current Project Status:
    • Proceeding into Design Development (DD) phase.
    • Selected Howard S. Wright through an RFP process for CMGC services.
    • Targeting middle of June 2024, to bid out all long lead items with the CMGC contractor, then bid all the remaining scopes out in November 2024.
    • Goal is to impact the staff/student as least as possible.

All Educational Facility Sites: Intercom & Clocks

ArchitectLandis Consulting
Contractor (CMGC)GB Manchester. The Electrical Contractor
Project Budgeton budget
Project Scheduleon Schedule
DesignJanuary 2024 – March 2026
BiddingApril 2024
ConstructionSummer 2024 – Summer 2026 (Multiple Summers)

Repairs/Renovations

  • Construction scheduled to commence June 2025 and be substantially completed in August 2025
  • Target Completion date: August 2025
DesignOngoing
BiddingTo Commence
May 2024
General ContractorTBD
Pre-ConstructionTBD
Bi-weekly meetingsTBD

Track Surface Upgrades

  • Construction scheduled to commence June 2024 and be substantially completed in August 2024
  • Target Completion date: August 2024
DesignComplete
BiddingComplete
General Contractor Beynon Sports
Pre-ConstructionOngoing with general contractor
Bi-weekly meetingsOngoing with staff to coordinate, communicate, and prepare for summer construction

All Educational Facility Sites: Intercom & Clocks

  • Construction is scheduled to commence in June 2024 and be substantially completed in July 2026. This scope will be at all educational facilities and will be completed over the next three summers. 
  • Target Completion date: Fall of 2024
  • Finalizing standards with DDSD stakeholders and the design teams.
DesignOngoing
BiddingOngoing