Floyd Light Middle School Bond Updates
Project Scope Summary
| Renovations | Amount | Start & End Date |
|---|---|---|
| Install generator and service lines | 7,000,000 | Feb. 2024 – Dec. 2025 |
| Upgrade building HVAC System | ||
| Remodel entry for a secure vestibule | ||
| Repair/ Replace Track Surface (Alice Ott, Floyd Light & Ron Russell) | 1,250,000 | July 2023 – Dec. 2024 |
| Upgrade Intercom Systems & Some Clock Systems (All Educational Facility Sites) | 8,005,000 | July 2023 – December 2026 |
October 2025
Construction Progress Photos
Before
After


Current Project Status
- Remodeled entry for a secure vestibule
- Installed generator and service lines
- Updated building HVAC system
July 2025
Current Construction Timeline
| Architect | BBL Architects |
| Contractor (CMGC) | Howard S. Wright |
| Construction | On Schedule to construct over summer 2025 |
Current Project Status
- Permit has been issued.
- Contractor has mobilized to site.
- Early May mobilization to site has benefitted overall project schedule.
- Project is currently on schedule.
- Project will not require a second phase for cooling due to capacity of existing electrical systems.
June 2025
Current Construction Timeline
| Architect | BBL Architects |
| Contractor (CMGC) | Howard S. Wright |
| Construction | Summer 2025 |
Current Project Status
- Staff are currently packing and preparing for the move, and everything is progressing according to schedule.
- The school building will be closed for the summer.
May 2025
Current Construction Timeline
| Architect | BBL Architects |
| Contractor (CMGC) | Howard S. Wright |
| Construction | Summer 2025 |
Current Project Status
- Permit has been issued.
- Contractor will mobilize to the site on June 16, 2025.
- Early exterior work will begin in May to ensure successful project completion.
- GMP has been established.
- Project will not require a second phase for cooling due to capacity of existing
electrical systems.
February 2025
| Architect | BBL Architects |
| Contractor (CMGC) | Howard S. Wright |
| Project Schedule | On Schedule |
| Design | Complete |
| Permit | Issued |
| Construction | Summer 2025 |
| Move Back In | Fall 2025 |
- Current Project Status:
- Long lead buyout is complete.
- Buyout for all remaining divisions is 95% complete, initial GMP is at/under budget.
- Goal is to impact the staff/student as least as possible.
- Project will not require a second phase for cooling due to capacity of existing electrical systems.
August 2024
| Architect | BBL Architects |
| Contractor (CMGC) | Howard S. Wright |
| Project Budget | on budget |
| Project Schedule | on Schedule |
| Pre-Design/Programming | November 2023 – January 2024 |
| Design | January 2024 – November 2024 |
| Permit | November 2024 – March 2025 |
| Bidding | June 2024 – November 2024 |
| Construction | Summer 2025 |
| Move Back In | Fall 2025 |
- Current Project Status:
- DD (Design Development) phase is complete.
- Team is working towards completion of 100% CD (Construction Document) set.
- Selected Howard S. Wright through an RFP process for CMGC services.
- Target of middle of June 2024 was met, to bid out all long lead items with the CMGC contractor, then bid all the remaining scopes out in November 2024.
- Goal is to impact the staff/student as little as possible.
May 2024
| Architect | BBL Architects |
| Contractor (CMGC) | Howard S. Wright |
| Project Budget | on budget |
| Project Schedule | on Schedule |
| Pre-Design/Programming | November 2023 – January 2024 |
| Design | January 2024 – November 2024 |
| Permit | November 2024 – March 2025 |
| Bidding | June 2024 – November 2024 |
| Construction | Summer 2025 |
| Owner Move Back In | Fall 2025 |
- Current Project Status:
- Proceeding into Design Development (DD) phase.
- Selected Howard S. Wright through an RFP process for CMGC services.
- Targeting middle of June 2024, to bid out all long lead items with the CMGC contractor, then bid all the remaining scopes out in November 2024.
- Goal is to impact the staff/student as least as possible.
All Educational Facility Sites: Intercom & Clocks
| Architect | Landis Consulting |
| Contractor (CMGC) | GB Manchester. The Electrical Contractor |
| Project Budget | on budget |
| Project Schedule | on Schedule |
| Design | January 2024 – March 2026 |
| Bidding | April 2024 |
| Construction | Summer 2024 – Summer 2026 (Multiple Summers) |
February 2024
Repairs/Renovations
- Construction scheduled to commence June 2025 and be substantially completed in August 2025
- Target Completion date: August 2025
| Design | Ongoing |
| Bidding | To Commence May 2024 |
| General Contractor | TBD |
| Pre-Construction | TBD |
| Bi-weekly meetings | TBD |
Track Surface Upgrades
- Construction scheduled to commence June 2024 and be substantially completed in August 2024
- Target Completion date: August 2024
| Design | Complete |
| Bidding | Complete |
| General Contractor | Beynon Sports |
| Pre-Construction | Ongoing with general contractor |
| Bi-weekly meetings | Ongoing with staff to coordinate, communicate, and prepare for summer construction |
All Educational Facility Sites: Intercom & Clocks
- Construction is scheduled to commence in June 2024 and be substantially completed in July 2026. This scope will be at all educational facilities and will be completed over the next three summers.
- Target Completion date: Fall of 2024
- Finalizing standards with DDSD stakeholders and the design teams.
| Design | Ongoing |
| Bidding | Ongoing |