Gilbert Heights Elementary School Bond Updates

Project Scope Summary

RenovationAmountStart & End Date
Remodel Main Office4,300,0002023–Dec. 2024
Remodel existing areas to include spaces for specialists
Replace most metal windows and sealant
Remodel entry for a secure vestibule
Replaced some siding and roofing
Upgrade Intercom Systems & Some Clock Systems (All Educational Facility Sites)8,005,000July 2023–December 2026

Current Construction Timeline

ArchitectAXIS Design
ContractorPar-Tech Construction
Project Budgeton budget
Project Scheduleon Schedule
PermitJanuary 2024 – May 2024
ConstructionSummer 2024
Move Back InFall 2024
  • Current Project Status –
    • Design/Bid Phase complete.
    • Permit submittal complete – Currently under review with City and anticipate permit approval middle of May 2024.
    • Construction mobilization phase is complete. 
    • Repair/Renovation scopes are ongoing, currently no concerns with finishing scopes of work over the summer schedule.
    • No District is onsite for the duration of the summer construction schedule. 
ArchitectAXIS Design
ContractorPar-Tech Construction
Project Budgeton budget
Project Scheduleon Schedule
PermitJanuary 2024 – May 2024
ConstructionSummer 2024
Owner Move Back InFall 2024
  • Current Project Status –
    • Design/Bid Phase complete.
    • Permit submittal complete – Currently under review with City and anticipate permit approval middle of May 2024.
    • Bids were received February 8, 2024 . Bids were a little over the target budget, but other project funds were used to fund the shortfall and Par-Tech Construction is under contract.
    • Pre-Construction meetings are ongoing to assure project success.
    • Ongoing communications with site staff on expectations for summers scopes of work continues

All Educational Facility Sites: Intercom & Clocks

ArchitectLandis Consulting
Contractor (CMGC)GB Manchester. The Electrical Contractor
Project Budgeton budget
Project Scheduleon Schedule
DesignJanuary 2024 – March 2026
BiddingApril 2024
ConstructionSummer 2024 – Summer 2026 (Multiple Summers)

Repairs/Renovations

  • Construction scheduled to commence June 2024 and be substantially completed in August 2024
  • Target Completion date: August 2024
DesignComplete
BiddingComplete
PermitSubmitted and under review with City of Portland
General ContractorPar-Tech Construction
Pre-ConstructionOngoing with general contractor
Bi-weekly meetingsOngoing with staff to coordinate, communicate, and prepare for summer construction

All Educational Facility Sites: Intercom & Clocks

  • Construction is scheduled to commence in June 2024 and be substantially completed in July 2026. This scope will be at all educational facilities and will be completed over the next three summers. 
  • Target Completion date: Fall of 2024
  • Finalizing standards with DDSD stakeholders and the design teams.
DesignOngoing
BiddingOngoing