Gilbert Park Elementary School Bond Updates
Project Scope Summary
| Renovations | Amount | Start & End Date |
|---|---|---|
| Remodel existing areas to include spaces for specialists | 2,900,000 | 2023 – Dec. 2024 |
| Replace a portion of the roof | ||
| Replace fire alarm system | ||
| Replace siding | ||
| Upgrade Intercom Systems & Some Clock Systems (All Educational Facility Sites) | 8,005,000 | July 2023 – December 2026 |
May 2025
Current Construction Timeline
| Architect | BBL Architects |
| Contractor (CMGC) | Selection process is underway |
| Construction | Summer 2026 |
Current Project Status
- Pre-Design/Scoping phase is underway.
January 2025
Project Updates
Stops for exterior vestibule glass doors should be done during winter break. Gilbert Park is complete. Some plywood in the gym was replaced.
December 2024
Project Updates
Stops for exterior vestibule glass doors should be done during winter break. The library door is missing a plate and will be remedied during winter break.
November 2024
Current Construction Timeline
| Architect | AXIS Design |
| Contractor | Par-Tech Construction |
| Project Budget | on budget |
| Project Schedule | Substatially Complete |
| Permit | January 2024 – May 2024 |
| Construction | Summer 2024 |
| Move Back In | Fall 2024 |
Current Project Status:
- Projects are substantially complete, and the team is working on punch list items and project closeout items.

October 2024
Dear Gilbert Park Elementary Families,
We want to extend our heartfelt thanks to all of you for supporting the 2022 Bond Measure for the David Douglas School District. Your commitment has enabled us to make meaningful improvements to our school, and we are excited to share the progress that has been made.
This past summer, Gilbert Park Elementary was busy with essential renovations to enhance our learning environment. Here are the critical updates:
- Specialist Spaces Remodel: Existing areas have been remodeled to create dedicated spaces for specialists, providing focused support for students.
- Roof Replacement: A portion of the roof has been replaced to enhance the building’s durability and weather protection.
- Fire Alarm System Replacement: A new fire alarm system has been installed to ensure safety and meet current standards.
- Siding Replacement: The siding has been replaced to improve the building’s exterior and ensure long-term resilience.
We are excited about these upgrades and their positive impact on our school’s future. Your continued support has made these improvements possible, and we deeply appreciate it.
Thank you once again for your dedication and partnership. Together, we are creating a better, more enriching learning experience for our students and a stronger future for our community.
Here are some before and after photos of the bond construction.
August 2024
| Architect | AXIS Design |
| Contractor | Par-Tech Construction |
| Project Budget | on budget |
| Project Schedule | on Schedule |
| Permit | January 2024 – May 2024 |
| Construction | Summer 2024 |
| Move Back In | Fall 2024 |
- Current Project Status –
- Design/Bid Phase complete.
- Permit submittal complete – Currently under review with City and anticipate permit approval middle of May 2024.
- Construction mobilization phase is complete.
- Repair/Renovation scopes are ongoing, currently no concerns with finishing scopes of work over the summer schedule.
- No District is onsite for the duration of the summer construction schedule.

Gilbert Park specialist spaces demolition

Gilbert Park roofing
May 2024
| Architect | AXIS Design |
| Contractor | Par-Tech Construction |
| Project Budget | on budget |
| Project Schedule | on Schedule |
| Permit | January 2024 – May 2024 |
| Construction | Summer 2024 |
| Owner Move Back In | Fall 2024 |
- Current Project Status –
- Design/Bid Phase complete.
- Permit submittal complete – Currently under review with City and anticipate permit approval middle of May 2024.
- Bids were received February 8, 2024 . Bids were a little over the target budget, but other project funds were used to fund the shortfall and Par-Tech Construction is under contract.
- Pre-Construction meetings are ongoing to assure project success.
- Ongoing communications with site staff on expectations for summers scopes of work continues
All Educational Facility Sites: Intercom & Clocks
| Architect | Landis Consulting |
| Contractor (CMGC) | GB Manchester. The Electrical Contractor |
| Project Budget | on budget |
| Project Schedule | on Schedule |
| Design | January 2024 – March 2026 |
| Bidding | April 2024 |
| Construction | Summer 2024 – Summer 2026 (Multiple Summers) |
February 2024
Repairs/Renovations
- Construction scheduled to commence June 2024 and be substantially completed in August 2024
- Target Completion date: August 2024
| Design | Complete |
| Bidding | Complete |
| Permit | Submitted and under review with City of Portland |
| General Contractor | Par-Tech Construction |
| Pre-Construction | Ongoing with general contractor |
| Bi-weekly meetings | Ongoing with staff to coordinate, communicate, and prepare for summer construction |
All Educational Facility Sites: Intercom & Clocks
- Construction is scheduled to commence in June 2024 and be substantially completed in July 2026. This scope will be at all educational facilities and will be completed over the next three summers.
- Target Completion date: Fall of 2024
- Finalizing standards with DDSD stakeholders and the design teams.
| Design | Ongoing |
| Bidding | Ongoing |