Mill Park Elementary School Bond Updates
Project Scope Summary
Renovations | Amount | Start & End Date |
---|---|---|
Remodel existing areas to include spaces for specialists | 3,925,000 | Feb. 2024 – Dec. 2025 |
Replace most windows | ||
Replace a portion of the roof | ||
Upgrade Intercom Systems & Some Clock Systems (All Educational Facility Sites) | 8,005,000 | July 2023 – December 2026 |
August 2024
Current Construction Timeline
Architect | Soderstrom Architects |
Contractor | TBD – Bid to prequalified GC’s |
Project Budget | on budget |
Project Schedule | on Schedule |
Pre-Design/Programming | March 2024 – July 2024 |
Design | July 2024 – December 2024 |
Permit | November 2024 – March 2025 |
Bidding | January 2024 |
Construction | Summer 2025 |
Move Back In | Fall 2025 |
- Current Project Status –
- Pre-design phase is nearing completion.
- Potentially adding HVAC and seismic upgrades to this scope of work with grant funds.
- Goal is to impact the staff/student as little as possible.
May 2024
Architect | Soderstrom Architects |
Contractor | TBD – Bid to prequalified GC’s |
Project Budget | on budget |
Project Schedule | on Schedule |
Pre-Design/Programming | February 2024 – March 2024 |
Design | April 2024 – November 2024 |
Permit | November 2024 – March 2025 |
Bidding | November 2024 |
Construction | Summer 2025 |
Owner Move Back In | Fall 2025 |
- Current Project Status –
- Finished up the predesign phase and proceeding into Design phase
- Potentially adding HVAC upgrades to this scope of work with grant funds
- Goal is to impact the staff/student as least as possible
All Educational Facility Sites: Intercom & Clocks
Architect | Landis Consulting |
Contractor (CMGC) | GB Manchester. The Electrical Contractor |
Project Budget | on budget |
Project Schedule | on Schedule |
Design | January 2024 – March 2026 |
Bidding | April 2024 |
Construction | Summer 2024 – Summer 2026 (Multiple Summers) |
February 2024
All Educational Facility Sites: Intercom & Clocks
- Construction is scheduled to commence in June 2024 and be substantially completed in July 2026. This scope will be at all educational facilities and will be completed over the next three summers.
- Target Completion date: Fall of 2024
- Finalizing standards with DDSD stakeholders and the design teams.
Design | Ongoing |
Bidding | Ongoing |