Mill Park Elementary School Bond Updates

Project Scope Summary

RenovationsAmountStart & End Date
Remodel existing areas to include spaces for specialists3,925,000Feb. 2024 – Dec. 2025
Replace most windows
Replace a portion of the roof
Upgrade Intercom Systems & Some Clock Systems (All Educational Facility Sites)8,005,000July 2023 – December 2026

Recent Updates on Building Construction

Interior of a school under construction, with exposed walls.
Before
Interior of a completed school building, with finished walls, clean floors, and installed lighting.
After

Current Project Status

  • Updates to the office in the safety vestibule 
  • Remodeled existing areas to include spaces for specialists
  • Replaced most windows
  • Replaced a portion of the roof 
  • Seismic upgrade 

Current Construction Timeline

ArchitectSoderstrom Architects
ContractorPar-Tech Construction
ConstructionOn Schedule to construct over summer 2025

Current Project Status

  • Permit has been issued.
  • Contractor has mobilized to site.
  • Project is currently on schedule.

Current Construction Timeline

ArchitectSoderstrom Architects
ContractorPar-Tech Construction
ConstructionSummer 2025

Current Project Status

  • Scheduled for construction over the next two summers.
  • The permit has been issued; however, it does not include the required tree inspection.
  • During the review process, the arborist reports were inadvertently missed by the plan reviewer. As a result, a tree inspection cannot be scheduled at this time. The plan reviewer is working to resolve this issue within the week.
  • No immediate delays are anticipated, as inspections are not currently needed.
  • The school building will be closed for the summer. 

Current Construction Timeline

ArchitectSoderstrom Architects
ContractorPar-Tech Construction
ConstructionSummer 2025


Current Project Status

  • Permit is under review with City of Portland.
  • Added HVAC and Seismic upgrades to this scope of work with grant funds.
  • Bond scope will be Summer 2025, along with added seismic upgrade scope.
  • HVAC scope will be moved to 2026 due to large volume of work and condensed
    Summer schedule, project will utilize the CM/GC delivery method.
  • Contractor will mobilize to the site on June 16, 2025.

Project Updates

This project is out to bid and will be brought for Board approval in February. Note that we have split this
into two projects for summer 2025 and summer 2026.

Project Updates

We are working on plans for the HVAC replacement, seismic upgrade, remodeling specialist spaces, window upgrades and some roofing replacement. We are currently determining the best way to spread this work over two summers. The amount of work is simply too much to complete within 9 weeks in summer.

ArchitectSoderstrom Architects
ContractorTBD – Bid to prequalified GC’s
Project Budgeton budget
Project Scheduleon Schedule
Pre-Design/ProgrammingMarch 2024 – July 2024
DesignJuly 2024 – December 2024
PermitNovember 2024 – March 2025
BiddingJanuary 2024
ConstructionSummer 2025
Move Back InFall 2025
  • Current Project Status:
    • Pre-design phase is nearing completion. 
    • Added HVAC and Seismic upgrades to this scope of work with grant funds.
    • Goal is to impact the staff/student as least as possible.
    • Project will have a second phase for electrical upgrade and cooling start-up due to long lead procurement items. 
ArchitectSoderstrom Architects
ContractorTBD – Bid to prequalified GC’s
Project Budgeton budget
Project Scheduleon Schedule
Pre-Design/ProgrammingMarch 2024 – July 2024
DesignJuly 2024 – December 2024
PermitNovember 2024 – March 2025
BiddingJanuary 2024
ConstructionSummer 2025
Move Back InFall 2025
  • Current Project Status –
    • Pre-design phase is nearing completion. 
    • Potentially adding HVAC and seismic upgrades to this scope of work with grant funds.
    • Goal is to impact the staff/student as little as possible.
ArchitectSoderstrom Architects
ContractorTBD – Bid to prequalified GC’s
Project Budgeton budget
Project Scheduleon Schedule
Pre-Design/ProgrammingFebruary 2024 – March 2024
DesignApril 2024 – November 2024
PermitNovember 2024 – March 2025
BiddingNovember 2024
ConstructionSummer 2025
Owner Move Back InFall 2025
  • Current Project Status –
    • Finished up the predesign phase and proceeding into Design phase
    • Potentially adding HVAC upgrades to this scope of work with grant funds
    • Goal is to impact the staff/student as least as possible

All Educational Facility Sites: Intercom & Clocks

ArchitectLandis Consulting
Contractor (CMGC)GB Manchester. The Electrical Contractor
Project Budgeton budget
Project Scheduleon Schedule
DesignJanuary 2024 – March 2026
BiddingApril 2024
ConstructionSummer 2024 – Summer 2026 (Multiple Summers)

All Educational Facility Sites: Intercom & Clocks

  • Construction is scheduled to commence in June 2024 and be substantially completed in July 2026. This scope will be at all educational facilities and will be completed over the next three summers. 
  • Target Completion date: Fall of 2024
  • Finalizing standards with DDSD stakeholders and the design teams.
DesignOngoing
BiddingOngoing