Remodel existing areas to include spaces for specialists
3,925,000
Feb. 2024 – Dec. 2025
Replace most windows
Replace a portion of the roof
Upgrade Intercom Systems & Some Clock Systems (All Educational Facility Sites)
8,005,000
July 2023 – December 2026
October 2025
Recent Updates on Building Construction
Before
After
Current Project Status
Updates to the office in the safety vestibule
Remodeled existing areas to include spaces for specialists
Replaced most windows
Replaced a portion of the roof
Seismic upgrade
July 2025
Current Construction Timeline
Architect
Soderstrom Architects
Contractor
Par-Tech Construction
Construction
On Schedule to construct over summer 2025
Current Project Status
Permit has been issued.
Contractor has mobilized to site.
Project is currently on schedule.
June 2025
Current Construction Timeline
Architect
Soderstrom Architects
Contractor
Par-Tech Construction
Construction
Summer 2025
Current Project Status
Scheduled for construction over the next two summers.
The permit has been issued; however, it does not include the required tree inspection.
During the review process, the arborist reports were inadvertently missed by the plan reviewer. As a result, a tree inspection cannot be scheduled at this time. The plan reviewer is working to resolve this issue within the week.
No immediate delays are anticipated, as inspections are not currently needed.
The school building will be closed for the summer.
May 2025
Current Construction Timeline
Architect
Soderstrom Architects
Contractor
Par-Tech Construction
Construction
Summer 2025
Current Project Status
Permit is under review with City of Portland.
Added HVAC and Seismic upgrades to this scope of work with grant funds.
Bond scope will be Summer 2025, along with added seismic upgrade scope.
HVAC scope will be moved to 2026 due to large volume of work and condensed Summer schedule, project will utilize the CM/GC delivery method.
Contractor will mobilize to the site on June 16, 2025.
January 2025
Project Updates
This project is out to bid and will be brought for Board approval in February. Note that we have split this into two projects for summer 2025 and summer 2026.
December 2024
Project Updates
We are working on plans for the HVAC replacement, seismic upgrade, remodeling specialist spaces, window upgrades and some roofing replacement. We are currently determining the best way to spread this work over two summers. The amount of work is simply too much to complete within 9 weeks in summer.
November 2024
Architect
Soderstrom Architects
Contractor
TBD – Bid to prequalified GC’s
Project Budget
on budget
Project Schedule
on Schedule
Pre-Design/Programming
March 2024 – July 2024
Design
July 2024 – December 2024
Permit
November 2024 – March 2025
Bidding
January 2024
Construction
Summer 2025
Move Back In
Fall 2025
Current Project Status:
Pre-design phase is nearing completion.
Added HVAC and Seismic upgrades to this scope of work with grant funds.
Goal is to impact the staff/student as least as possible.
Project will have a second phase for electrical upgrade and cooling start-up due to long lead procurement items.
August 2024
Architect
Soderstrom Architects
Contractor
TBD – Bid to prequalified GC’s
Project Budget
on budget
Project Schedule
on Schedule
Pre-Design/Programming
March 2024 – July 2024
Design
July 2024 – December 2024
Permit
November 2024 – March 2025
Bidding
January 2024
Construction
Summer 2025
Move Back In
Fall 2025
Current Project Status –
Pre-design phase is nearing completion.
Potentially adding HVAC and seismic upgrades to this scope of work with grant funds.
Goal is to impact the staff/student as little as possible.
May 2024
Architect
Soderstrom Architects
Contractor
TBD – Bid to prequalified GC’s
Project Budget
on budget
Project Schedule
on Schedule
Pre-Design/Programming
February 2024 – March 2024
Design
April 2024 – November 2024
Permit
November 2024 – March 2025
Bidding
November 2024
Construction
Summer 2025
Owner Move Back In
Fall 2025
Current Project Status –
Finished up the predesign phase and proceeding into Design phase
Potentially adding HVAC upgrades to this scope of work with grant funds
Goal is to impact the staff/student as least as possible
All Educational Facility Sites: Intercom & Clocks
Architect
Landis Consulting
Contractor (CMGC)
GB Manchester. The Electrical Contractor
Project Budget
on budget
Project Schedule
on Schedule
Design
January 2024 – March 2026
Bidding
April 2024
Construction
Summer 2024 – Summer 2026 (Multiple Summers)
February 2024
All Educational Facility Sites: Intercom & Clocks
Construction is scheduled to commence in June 2024 and be substantially completed in July 2026. This scope will be at all educational facilities and will be completed over the next three summers.
Target Completion date: Fall of 2024
Finalizing standards with DDSD stakeholders and the design teams.