North Powellhurst Bond Updates
Project Scope Summary
Renovations | Amount | Start & End Date |
---|---|---|
Replace and repair failing exterior finishes | 5,850,000 | July 2023 – Dec. 2024 |
Replace windows | ||
Remodel/renovate for preschool class- rooms | ||
Replace a portion of the plumbing | ||
Remodel entry for a secure vestibule Electrical systems upgrades | ||
Upgrade Intercom Systems & Some Clock Systems (All Educational Facility Sites) | 8,005,000 | July 2023 – December 2026 |
August 2024
Current Construction Timeline
Architect | BBL Architect |
Contractor | Brockamp & Jaeger General Contractor |
Project Budget | on budget |
Project Schedule | on Schedule |
Permit | November 2023 – April 2024 |
Construction | Summer 2024 |
Move Back In | Fall 2024 |
- Current Project Status –
- Design/Bid Phase complete.
- Permits are approved and issued.
- Construction mobilization phase is complete.
- Repair/Renovation scopes are ongoing, currently no concerns with finishing scopes of work over the summer schedule.
- No District staff onsite for duration of summer construction schedule.
May 2024
Architect | BBL Architect |
Contractor | Brockamp & Jaeger General Contractor |
Project Budget | on budget |
Project Schedule | on Schedule |
Permit | November 2023 – April 2024 |
Construction | Summer 2024 |
Owner Move Back In | Fall 2024 |
- Current Project Status –
- Design/Bid Phase complete.
- Permits are approved and issued.
- Bids were received January 18, 2024 . Bids were under the target budget and the contract was awarded to Brockamp & Jaeger.
- Pre-Construction meetings are ongoing to assure project success.
- Ongoing communications with site staff on expectations for summers scopes of work continues
All Educational Facility Sites: Intercom & Clocks
Architect | Landis Consulting |
Contractor (CMGC) | GB Manchester. The Electrical Contractor |
Project Budget | on budget |
Project Schedule | on Schedule |
Design | January 2024 – March 2026 |
Bidding | April 2024 |
Construction | Summer 2024 – Summer 2026 (Multiple Summers) |
February 2024
Repairs/Renovations
- Construction scheduled to commence June 2024 and be substantially complete August 2024
- Target Completion date – August 2024
Design | Complete |
Bidding | Complete |
Permit | Submitted and under review with City of Portland |
General Contractor | Brockamp & Jaeger |
Pre-Construction | Ongoing with general contractor |
Bi-weekly meetings | Ongoing with staff to coordinate, communicate, and prepare for summer construction |
All Educational Facility Sites: Intercom & Clocks
- Construction is scheduled to commence in June 2024 and be substantially completed in July 2026. This scope will be at all educational facilities and will be completed over the next three summers.
- Target Completion date: Fall of 2024
- Finalizing standards with DDSD stakeholders and the design teams.
Design | Ongoing |
Bidding | Ongoing |