North Powellhurst Bond Updates
Project Scope Summary
Renovations | Amount | Start & End Date |
---|---|---|
Replace and repair failing exterior finishes | 5,850,000 | July 2023 – Dec. 2024 |
Replace windows | ||
Remodel/renovate for preschool class- rooms | ||
Replace a portion of the plumbing | ||
Remodel entry for a secure vestibule Electrical systems upgrades | ||
Upgrade Intercom Systems & Some Clock Systems (All Educational Facility Sites) | 8,005,000 | July 2023 – December 2026 |
February 2025
Current Project Status
- Project is substantially complete and final punch items completed over winter break.
- Close out documents completed and distributed to District.
- Electrical Upgrades completed over winter break.
- Through-wall AC units are now operable.
January 2025
Project Updates
We are looking at some workmanship on flooring in the restroom, but otherwise all work is completed.
We will be adding some shades to transom windows over doors.
December 2024
Project Updates
The electrical upgrade is planned for the week of December 23rd and is on target. The ADA operator will be installed during the break. Hydroseeding and access controls have been completed. One bathroom has some corrections needed to the flooring and a urinal that also will occur during the break.
November 2024
Current Construction Timeline
Architect | BBL Architect |
Contractor | Brockamp & Jaeger General Contractor |
Project Budget | on budget |
Project Schedule | Substantially Complete |
Permit | November 2023 – April 2024 |
Construction | Summer 2024 |
Move Back In | Fall 2024 |
- Current Project Status:
- Project is substantially complete, and team is working on punch list items and project closeout items.
- Electrical Upgrades are scheduled for winter break
- Air-Conditioned space scope scheduled for spring break


October 2024
Dear North Powellhurst Elementary Families,
We are grateful for your overwhelming support of the 2022 Bond Measure for the David Douglas School District. Thanks to your commitment, we are making essential upgrades and renovations that will benefit our students, staff, and community for years to come.
This summer, North Powellhurst School Building began several renovation projects, and we’re excited to share the progress:
- Exterior Finishes: Failing exterior finishes have been replaced and repaired to improve the building’s durability and appearance.
- Window Replacement: New windows have been installed to enhance energy efficiency and overall comfort.
- Preschool Classroom Remodel: Preschool classrooms have been remodeled and renovated to create better learning spaces.
- Plumbing Replacement: A portion of the plumbing system has been replaced for improved reliability.
- Secure Vestibule Remodel: The entry has been remodeled to include a secure vestibule for enhanced safety and access control.
- Electrical System Upgrades: Electrical systems have been upgraded to meet modern standards and improve efficiency.
These improvements are critical to creating a safer, more modern, and engaging environment for our students and staff. We are grateful for your continued support in making these essential upgrades possible.
Once again, thank you for your commitment to the future of North Powellhurst Elementary. Together, we are building a brighter, safer, and more enriching environment for our students.
Here are some before and after photos of the bond construction.
August 2024
Architect | BBL Architect |
Contractor | Brockamp & Jaeger General Contractor |
Project Budget | on budget |
Project Schedule | on Schedule |
Permit | November 2023 – April 2024 |
Construction | Summer 2024 |
Move Back In | Fall 2024 |
- Current Project Status –
- Design/Bid Phase complete.
- Permits are approved and issued.
- Construction mobilization phase is complete.
- Repair/Renovation scopes are ongoing, currently no concerns with finishing scopes of work over the summer schedule.
- No District staff onsite for duration of summer construction schedule.

Demolition of Pre-k classroom casework

Demolition of existing windows
May 2024
Architect | BBL Architect |
Contractor | Brockamp & Jaeger General Contractor |
Project Budget | on budget |
Project Schedule | on Schedule |
Permit | November 2023 – April 2024 |
Construction | Summer 2024 |
Owner Move Back In | Fall 2024 |
- Current Project Status –
- Design/Bid Phase complete.
- Permits are approved and issued.
- Bids were received January 18, 2024 . Bids were under the target budget and the contract was awarded to Brockamp & Jaeger.
- Pre-Construction meetings are ongoing to assure project success.
- Ongoing communications with site staff on expectations for summers scopes of work continues
All Educational Facility Sites: Intercom & Clocks
Architect | Landis Consulting |
Contractor (CMGC) | GB Manchester. The Electrical Contractor |
Project Budget | on budget |
Project Schedule | on Schedule |
Design | January 2024 – March 2026 |
Bidding | April 2024 |
Construction | Summer 2024 – Summer 2026 (Multiple Summers) |
February 2024
Repairs/Renovations
- Construction scheduled to commence June 2024 and be substantially complete August 2024
- Target Completion date – August 2024
Design | Complete |
Bidding | Complete |
Permit | Submitted and under review with City of Portland |
General Contractor | Brockamp & Jaeger |
Pre-Construction | Ongoing with general contractor |
Bi-weekly meetings | Ongoing with staff to coordinate, communicate, and prepare for summer construction |
All Educational Facility Sites: Intercom & Clocks
- Construction is scheduled to commence in June 2024 and be substantially completed in July 2026. This scope will be at all educational facilities and will be completed over the next three summers.
- Target Completion date: Fall of 2024
- Finalizing standards with DDSD stakeholders and the design teams.
Design | Ongoing |
Bidding | Ongoing |