Ron Russell Middle School Bond Updates
Project Scope Summary
Renovations | Amount | Start & End Date |
---|---|---|
Replace portion of the roofing | 3,500,000 | Dec. 2025 – Dec. 2026 |
Remodel entry for a secure vestibule | ||
Upgrade Intercom Systems & Some Clock Systems (All Educational Facility Sites) | 8,005,000 | July 2023 – December 2026 |
February 2024
Current Construction Timeline
Track Surface Upgrades
- Construction scheduled to commence June 2024 and be substantially completed in August 2024
- Target Completion date: August 2024
Design | Complete |
Bidding | Complete |
General Contractor | Beynon Sports |
Pre-Construction | Ongoing with general contractor |
Bi-weekly meetings | Ongoing with staff to coordinate, communicate, and prepare for summer construction |
All Educational Facility Sites: Intercom & Clocks
- Construction is scheduled to commence in June 2024 and be substantially completed in July 2026. This scope will be at all educational facilities and will be completed over the next three summers.
- Target Completion date: Fall of 2024
- Finalizing standards with DDSD stakeholders and the design teams.
Design | Ongoing |
Bidding | Ongoing |