Ron Russell Middle School Bond Updates

Project Scope Summary

RenovationsAmountStart & End Date
Replace portion of the roofing3,500,000Dec. 2025 – Dec. 2026
Remodel entry for a secure vestibule
Upgrade Intercom Systems & Some Clock Systems (All Educational Facility Sites)8,005,000July 2023 – December 2026

Current Construction Timeline

Track Surface Upgrades

  • Construction scheduled to commence June 2024 and be substantially completed in August 2024
  • Target Completion date: August 2024
DesignComplete
BiddingComplete
General Contractor Beynon Sports
Pre-ConstructionOngoing with general contractor
Bi-weekly meetingsOngoing with staff to coordinate, communicate, and prepare for summer construction

All Educational Facility Sites: Intercom & Clocks

  • Construction is scheduled to commence in June 2024 and be substantially completed in July 2026. This scope will be at all educational facilities and will be completed over the next three summers. 
  • Target Completion date: Fall of 2024
  • Finalizing standards with DDSD stakeholders and the design teams.
DesignOngoing
BiddingOngoing