South Powellhurst Bond Updates

Project Scope Summary

RenovationAmountStart & End Date
Replace tile flooring5,250,000Dec. 2025 – Dec. 2026
Replace fire alarm system
Upgrade HVAC
Repair sewer line
Upgrade Intercom Systems & Some Clock Systems (All Educational Facility Sites)8,005,000July 2023 – December 2026

Current Construction Timeline

ArchitectBBL Architects
Contractor (CMGC)Howard S. Wright
Project Budgeton budget
Project Scheduleon Schedule
Pre-Design/Programming January 2024 – March 2024
DesignApril 2024 – November 2024
PermitNovember 2024 – March 2025
BiddingJune 2024 – January 2025
ConstructionSummer 2025
Move Back InFall 2025
  • Current Project Status –
    • Moved this project up a year to combine with other project CMGC efforts. This is due to ongoing long lead procurement challenges. 
    • Finalizing the pre-design phase.
    • Selected Howard S. Wright through an RFP process for CMGC services.
    • Target of middle of June 2024 was met, to bid out all long lead items with the CMGC contractor, then bid all the remaining scopes out in November 2024. 
    • Goal is to impact the staff/student as little as possible.
ArchitectBBL Architects
Contractor (CMGC)Howard S. Wright
Project Budgeton budget
Project Scheduleon Schedule
Pre-Design/Programming January 2024 – March 2024
DesignApril 2024 – November 2024
PermitNovember 2024 – March 2025
BiddingJune 2024 – November 2024
ConstructionSummer 2025
Owner Move Back InFall 2025
  • Current Project Status –
    • Moved this project up a year to combine with other project CMGC efforts. This is due to ongoing long lead procurement challenges.
    • Finalizing the pre-design phase.
    • Selected Howard S. Wright through an RFP process for CMGC services.
    • Targeting middle of June 2024, to bid out all long lead items with the CMGC contractor, then bid all the remaining scopes out in November 2024.
    • Goal is to impact the staff/student as least as possible.

All Educational Facility Sites: Intercom & Clocks

ArchitectLandis Consulting
Contractor (CMGC)GB Manchester. The Electrical Contractor
Project Budgeton budget
Project Scheduleon Schedule
DesignJanuary 2024 – March 2026
BiddingApril 2024
ConstructionSummer 2024 – Summer 2026 (Multiple Summers)

All Educational Facility Sites: Intercom & Clocks

  • Construction is scheduled to commence in June 2024 and be substantially completed in July 2026. This scope will be at all educational facilities and will be completed over the next three summers. 
  • Target Completion date: Fall of 2024
  • Finalizing standards with DDSD stakeholders and the design teams.
DesignOngoing
BiddingOngoing