South Powellhurst Bond Updates
Project Scope Summary
Renovation | Amount | Start & End Date |
---|---|---|
Replace tile flooring | 5,250,000 | Dec. 2025 – Dec. 2026 |
Replace fire alarm system | ||
Upgrade HVAC | ||
Repair sewer line | ||
Upgrade Intercom Systems & Some Clock Systems (All Educational Facility Sites) | 8,005,000 | July 2023 – December 2026 |
August 2024
Current Construction Timeline
Architect | BBL Architects |
Contractor (CMGC) | Howard S. Wright |
Project Budget | on budget |
Project Schedule | on Schedule |
Pre-Design/Programming | January 2024 – March 2024 |
Design | April 2024 – November 2024 |
Permit | November 2024 – March 2025 |
Bidding | June 2024 – January 2025 |
Construction | Summer 2025 |
Move Back In | Fall 2025 |
- Current Project Status –
- Moved this project up a year to combine with other project CMGC efforts. This is due to ongoing long lead procurement challenges.
- Finalizing the pre-design phase.
- Selected Howard S. Wright through an RFP process for CMGC services.
- Target of middle of June 2024 was met, to bid out all long lead items with the CMGC contractor, then bid all the remaining scopes out in November 2024.
- Goal is to impact the staff/student as little as possible.
May 2024
Architect | BBL Architects |
Contractor (CMGC) | Howard S. Wright |
Project Budget | on budget |
Project Schedule | on Schedule |
Pre-Design/Programming | January 2024 – March 2024 |
Design | April 2024 – November 2024 |
Permit | November 2024 – March 2025 |
Bidding | June 2024 – November 2024 |
Construction | Summer 2025 |
Owner Move Back In | Fall 2025 |
- Current Project Status –
- Moved this project up a year to combine with other project CMGC efforts. This is due to ongoing long lead procurement challenges.
- Finalizing the pre-design phase.
- Selected Howard S. Wright through an RFP process for CMGC services.
- Targeting middle of June 2024, to bid out all long lead items with the CMGC contractor, then bid all the remaining scopes out in November 2024.
- Goal is to impact the staff/student as least as possible.
All Educational Facility Sites: Intercom & Clocks
Architect | Landis Consulting |
Contractor (CMGC) | GB Manchester. The Electrical Contractor |
Project Budget | on budget |
Project Schedule | on Schedule |
Design | January 2024 – March 2026 |
Bidding | April 2024 |
Construction | Summer 2024 – Summer 2026 (Multiple Summers) |
February 2024
All Educational Facility Sites: Intercom & Clocks
- Construction is scheduled to commence in June 2024 and be substantially completed in July 2026. This scope will be at all educational facilities and will be completed over the next three summers.
- Target Completion date: Fall of 2024
- Finalizing standards with DDSD stakeholders and the design teams.
Design | Ongoing |
Bidding | Ongoing |