South Powellhurst Bond Updates
Project Scope Summary
| Renovation | Amount | Start & End Date |
|---|---|---|
| Replace tile flooring | 5,250,000 | Dec. 2025 – Dec. 2026 |
| Replace fire alarm system | ||
| Upgrade HVAC | ||
| Repair sewer line | ||
| Upgrade Intercom Systems & Some Clock Systems (All Educational Facility Sites) | 8,005,000 | July 2023 – December 2026 |
October 2025
Recent Updates on Building Construction
Current Project Status
- Replaced the tile flooring
- Replaced the fire alarm system
- Upgraded HVAC system
July 2025
Current Construction Timeline
| Architect | BBL Architects |
| Contractor (CMGC) | Howard S. Wright |
| Construction | On Schedule to construct over summer 2025 |
Current Project Status
- Permit has been issued.
- Contractor has mobilized to site.
- Project is currently on schedule.
June 2025
Current Construction Timeline
| Architect | BBL Architects |
| Contractor (CMGC) | Howard S. Wright |
| Construction | Summer 2025 |
Current Project Status
- Staff are currently packing and preparing for the move, and everything is progressing according to schedule.
- The school building will be closed for the summer.
May 2025
Current Construction Timeline
| Architect | BBL Architects |
| Contractor (CMGC) | Howard S. Wright |
| Construction | Summer 2025 |
Current Project Status
- Permit has been issued.
- Contractor will mobilize to the site on June 16, 2025.
- GMP has been established.
February 2025
| Architect | BBL Architects |
| Contractor (CMGC) | Howard S. Wright |
| Project Schedule | On Schedule |
| Design | Complete |
| Permit | Under Review with City of Portland |
| Bidding | Buyout process underway, will be validated by mid-February |
| Construction | Summer 2025 |
| Move Back In | Fall 2025 |
- Current Project Status
- Goal is to impact staff/students as least as possible.
- No long lead items identified.
August 2024
| Architect | BBL Architects |
| Contractor (CMGC) | Howard S. Wright |
| Project Budget | on budget |
| Project Schedule | on Schedule |
| Pre-Design/Programming | January 2024 – March 2024 |
| Design | April 2024 – November 2024 |
| Permit | November 2024 – March 2025 |
| Bidding | June 2024 – January 2025 |
| Construction | Summer 2025 |
| Move Back In | Fall 2025 |
- Current Project Status –
- Moved this project up a year to combine with other project CMGC efforts. This is due to ongoing long lead procurement challenges.
- Finalizing the pre-design phase.
- Selected Howard S. Wright through an RFP process for CMGC services.
- Target of middle of June 2024 was met, to bid out all long lead items with the CMGC contractor, then bid all the remaining scopes out in November 2024.
- Goal is to impact the staff/student as little as possible.
May 2024
| Architect | BBL Architects |
| Contractor (CMGC) | Howard S. Wright |
| Project Budget | on budget |
| Project Schedule | on Schedule |
| Pre-Design/Programming | January 2024 – March 2024 |
| Design | April 2024 – November 2024 |
| Permit | November 2024 – March 2025 |
| Bidding | June 2024 – November 2024 |
| Construction | Summer 2025 |
| Owner Move Back In | Fall 2025 |
- Current Project Status –
- Moved this project up a year to combine with other project CMGC efforts. This is due to ongoing long lead procurement challenges.
- Finalizing the pre-design phase.
- Selected Howard S. Wright through an RFP process for CMGC services.
- Targeting middle of June 2024, to bid out all long lead items with the CMGC contractor, then bid all the remaining scopes out in November 2024.
- Goal is to impact the staff/student as least as possible.
All Educational Facility Sites: Intercom & Clocks
| Architect | Landis Consulting |
| Contractor (CMGC) | GB Manchester. The Electrical Contractor |
| Project Budget | on budget |
| Project Schedule | on Schedule |
| Design | January 2024 – March 2026 |
| Bidding | April 2024 |
| Construction | Summer 2024 – Summer 2026 (Multiple Summers) |
February 2024
All Educational Facility Sites: Intercom & Clocks
- Construction is scheduled to commence in June 2024 and be substantially completed in July 2026. This scope will be at all educational facilities and will be completed over the next three summers.
- Target Completion date: Fall of 2024
- Finalizing standards with DDSD stakeholders and the design teams.
| Design | Ongoing |
| Bidding | Ongoing |