Ventura Park Elementary School Bond Updates
Project Scope Summary
Renovations | Amount | Start & End Date |
---|---|---|
Remodel existing areas to include spaces for specialists | 1,925,000 | Feb. 2025 – Dec. 2026 |
Replace fire alarm system | ||
Remodel entry for a secure vestibule | ||
Upgrade Intercom Systems & Some Clock Systems (All Educational Facility Sites) | 8,005,000 | July 2023 – December 2026 |
February 2024
Current Construction Timeline
All Educational Facility Sites: Intercom & Clocks
- Construction is scheduled to commence in June 2024 and be substantially completed in July 2026. This scope will be at all educational facilities and will be completed over the next three summers.
- Target Completion date: Fall of 2024
- Finalizing standards with DDSD stakeholders and the design teams.
Design | Ongoing |
Bidding | Ongoing |