Remodel existing areas to include spaces for specialists
Remodel entry for a secure vestibule
Replace fire alarm system
Upgrade Intercom Systems & Some Clock Systems (All Educational Facility Sites)
8,005,000
July 2023 – December 2026
October 2025
Recent Updates on Building Construction
Before
After
Current Project Status
Upgraded the HVAC system
Remodeled existing areas to include spaces for specialists
Remodeled entry for a secure vestibule
Replaced the fire alarm system
July 2025
Current Construction Timeline
Architect
BBL Architects
Contractor (CMGC)
Howard S. Wright
Construction
On Schedule to construct over summer 2025
Current Project Status
Permit has been issued.
Early work in May has greatly benefitted project schedule. Currently in PGE queue for inspection and energization of new electrical gear.
Contractor has mobilized to site.
Project is currently on schedule.
Project will not require a second phase for cooling components due to CM/GC
June 2025
Current Construction Timeline
Architect
BBL Architects
Contractor (CMGC)
Howard S. Wright
Construction
Summer 2025
Current Project Status
Staff are currently packing and preparing for the move, and everything is progressing according to schedule.
The school building will be closed for the summer.
May 2025
Current Construction Timeline
Architect
BBL Architects
Contractor (CMGC)
Howard S. Wright
Construction
Summer 2025
Current Project Status
Permit has been issued.
Contractor will mobilize to the site on June 16, 2025.
Early work in May will occur to ensure successful electrical upgrade.
GMP has been established.
Project will not require a second phase for cooling components due to CM/GC procurement process.
February 2025
Architect
BBL Architects
Contractor (CMGC)
Howard S. Wright
Project Schedule
On Schedule
Design
Complete
Permit
Issued
Construction
Summer 2025
Move Back In
Fall 2025
Current Project Status:
Electrical scope buyout is complete, long lead items have been ordered.
Buyout for all remaining divisions is 95% complete, initial GMP is at/under budget.
Project will not require a second phase for cooling components due to CM/GC procurement process.
January 2025
Project Updates
Should have final bid numbers in February.
December 2024
Project Updates
West Powellhurst renovation designs are in process and include replacing the HVAC system, remodeling specialist spaces, adding a secure vestibule, and replacing the fire alarm system. We will be removing and reinstalling classroom casework as well as looking at an alternate for VRF integration.
November 2024
Architect
BBL Architects
Contractor (CMGC)
Howard S. Wright
Project Budget
on budget
Project Schedule
on Schedule
Pre-Design/Programming
November 2023 – January 2024
Design
January 2024 – July 2024
Permit
July 2024 – January 2025
Bidding
June 2024 – October 2024
Construction
Summer 2025
Move Back In
Fall 2025
Current Project Status:
Design phase is complete.
Electrical scope buyout is complete, long lead items have been ordered.
Mechanical bidding is in process.
Goal is to impact the staff/student as least as possible.
Project will not require a second phase for cooling components due to CM/GC procurement process.
May 2024
Architect
BBL Architects
Contractor (CMGC)
Howard S. Wright
Project Budget
on budget
Project Schedule
on Schedule
Pre-Design/Programming
November 2023 – January 2024
Design
January 2024 – November 2024
Permit
November 2024 – March 2025
Bidding
November 2024
Construction
Summer 2025
Owner Move Back In
Fall 2025
Current Project Status –
Proceeding into Design Development (DD) phase
Selected Howard S. Wright through an RFP process for CMGC services.
Targeting middle of June 2024, to bid out all long lead items with the CMGC contractor, then bid all the remaining scopes out in November 2024.
Goal is to impact the staff/student as least as possible
All Educational Facility Sites: Intercom & Clocks
Architect
Landis Consulting
Contractor (CMGC)
GB Manchester. The Electrical Contractor
Project Budget
on budget
Project Schedule
on Schedule
Design
January 2024 – March 2026
Bidding
April 2024
Construction
Summer 2024 – Summer 2026 (Multiple Summers)
February 2024
Construction scheduled to commence June 2025 and be substantially complete August 2025
Target Completion date – August 2025
Repairs/Renovations
Design
Ongoing
Bidding
To Commence May 2024
General Contractor
TBD
Pre-Construction
TBD
Bi-weekly meetings
TBD
All Educational Facility Sites: Intercom & Clocks
Construction is scheduled to commence in June 2024 and be substantially completed in July 2026. This scope will be at all educational facilities and will be completed over the next three summers.
Target Completion date: Fall of 2024
Finalizing standards with DDSD stakeholders and the design teams.